Implementation Project Management Guide

Created by Lori A, Modified on Wed, 25 Mar at 3:07 PM by Lori A

New Project Milestone and Task Document

Internal reference. Full task breakdown, owners, timing, and PM notes for all 10 phases.


How to use this guide: Each section covers one phase of the 12-week implementation. Expand a section to see every task, who owns it, when it should happen, and any PM notes. Add-on sections (Advanced Journey, Custom Dev, Mobile, SFTP) are flagged inside the relevant phases and only apply to customers with those features.
Implementation Manager SAP Developer Cloud Architect Design Customer Partner / IT
Timeline overview
WeekPhaseKey deliverablesFP Est.Milestone
1-2Blueprint and ConfigurationSigned blueprint, config requirements confirmed, project plan agreed2.5hSigned Blueprint
2IntegrationSite created, firewall open, integration validated, SAP details in Bitwarden1.5hIntegration Complete
3-5TrainingAll 3 training sessions delivered, DTWs reviewed, customer trained on Admin/Design8.5hTraining Complete
Before loadCustomer Site SetupCategories, employees, email, topic pages, message templates, credentials set up-
7Data LoadProducts and Business Partners loaded in TEST, DTWs reviewed1hData Load Complete
4-8ConfigurationAll general config complete, pricing verified after data load6h
8-10Site DesignBanners, topic pages, message templates, favicon, logo all in place1h
9-10QA and UATFocusPoint internal QA complete, UAT session held, customer testing done3hTesting Complete
11-12Production and Go LiveProduction deployment, domain switch, SSL, Go Live checklist session10.5hGo Live
12+Post-production1 week check-in, help desk handoff30m
Phase 1 Blueprint and configuration Est. 2.5h FocusPoint
Week 1-2. Milestone: Signed Blueprint. Dependency chain: Signed Proposal → Config Session → Blueprint signed.
TaskOwnerTimingPM notes
Send signed proposal to customerImplementation ManagerWeek 1Triggers project kick-off
Add signed proposal to ClickUpImplementation ManagerWeek 1
Schedule Configuration SessionImplementation ManagerWeek 10.5h. Dep: Signed Proposal
Verify stakeholders and confirm attendeesImplementation ManagerWeek 1
Verify time/date of session with customerImplementation ManagerWeek 1
Move customer from Pre-Sales to Current ImplementationsImplementation ManagerWeek 1
Request Customer Integration Requirement from Partner/ITImplementation ManagerWeek 10.5h. Dep: Config Session
Go over Project Plan with customerImplementation ManagerWeek 1
Obtain configuration requirementsImplementation ManagerWeek 1
Convert config requirements to PDF and send to customerImplementation ManagerWeek 1
Blueprint agreed and signed by customerCustomerWeek 20.5h. Dep: Config Session
Add Blueprint to Customer Details in ClickUpImplementation ManagerWeek 2
Notify DM that Blueprint has been completedImplementation ManagerWeek 2
Phase 2 Integration Est. 1.5h FocusPoint
Week 2. Milestone: Integration Complete. If IP whitelisting is delayed past Week 2, flag immediately. Training cannot be scheduled until integration is validated.
TaskOwnerTimingPM notes
Submit ticket to create site to Cloud teamImplementation ManagerWeek 2Dep: Blueprint signed
Cloud team creates siteCloud ArchitectWeek 2
Cloud team tests siteCloud ArchitectWeek 2
Cloud team sends site and whitelist info to customerCloud ArchitectWeek 2
DM checks site is fully functionalImplementation ManagerWeek 2
Send App Server Space/Script to Partner/Customer/ITImplementation ManagerWeek 20.5h
Send firewall and whitelist informationImplementation ManagerWeek 2
Request SAP access details from customerImplementation ManagerWeek 2
Customer sends SAP access information to FocusPointCustomerWeek 22h. Dep: Send App Server
Verify IP has been whitelistedPartner / ITWeek 2
Verify ports are openPartner / ITWeek 2
Verify scripts are installedPartner / ITWeek 2
Validate Firewall is openImplementation ManagerWeek 21.5h. Dep: Customer integration info
Validate messages are workingImplementation ManagerWeek 2
Add Customer SAP details to BitwardenImplementation ManagerWeek 2
For SLSync only: validate SAP transactionPartner / ITWeek 2SLSync customers only
Phase 3 Training Est. 8.5h FocusPoint
Week 3-5. 3 training sessions total. Cannot schedule until integration is validated. Add-on sections below apply only where noted.
TaskOwnerTimingPM notes
Schedule all training sessionsImplementation ManagerWeek 30.5h. Dep: Integration complete
Send Catalog Excel Spreadsheet to customerImplementation ManagerWeek 30.5h. Dep: Schedule Training
Send DTW Training Sheets to customerImplementation ManagerWeek 3
SAP FP Item Config training sessionImplementation ManagerWeek 31.5h
FocusPoint Administration training sessionImplementation ManagerWeek 32.5h total for FP Training session
Cover Message Templates and Email set upImplementation ManagerWeek 3
Cover how to add Users and CategoriesImplementation ManagerWeek 3
Cover Design (Banners, Mega Menu, Footers, Social Media)DesignWeek 3
Cover Inbound/Outbound messages, Sales Order, How toImplementation ManagerWeek 3
Cover email set upImplementation ManagerWeek 3
Cover UATImplementation ManagerWeek 3
Cover how to set up PromotionsImplementation ManagerWeek 3
Sales Reps review and documentationImplementation ManagerWeek 3If applicable
Manager ApprovalsImplementation ManagerWeek 3If applicable
SAP Data Transfer Workbench training sessionImplementation ManagerWeek 41.5h. Dep: Send Training Docs
Cover how to fill out DTWsSAP DeveloperWeek 4
Cover how to load DTWsSAP DeveloperWeek 4
▶ Advanced Journey only
Schedule Advanced Journey Design sessionImplementation ManagerWeek 35h total. Dep: Set up Workflow
Internal design session with Design teamDesignWeek 3
Advanced Journey Design session with customerDesignWeek 3
Site design deliveryDesignWeek 3
Design follow-up sessionDesignWeek 3
▶ SFTP / External Images only
Create task to have SFTP added for clientImplementation ManagerWeek 4
Create SFTP for customerCloud ArchitectWeek 4
Provide SFTP info to client with FileZilla how-toImplementation ManagerWeek 4
Send Customer Bulk Image upload template with instructionsImplementation ManagerWeek 4
▶ Custom Development only
Gather full requirementsSAP DeveloperWeek 31h. Dep: Blueprint
Task to DevelopmentImplementation ManagerWeek 330min
Development to create, test and deploy changesSAP DeveloperWeek 7Dep: Task to Dev
FP testing of custom developmentImplementation ManagerWeek 8
Customer testing of custom developmentCustomerWeek 8
Return to Development if neededSAP DeveloperWeek 9
MOBILE: All customizations copied to MobileSAP DeveloperWeek 8Mobile customers only. Must be done before UAT.
Phase 4 Customer site requirements Customer owned
Before data load. PM should confirm all items complete before scheduling data load review. These are all customer-owned tasks.
TaskOwnerTimingPM notes
Add additional Employees if applicableCustomerBefore load
Add and export CategoriesCustomerBefore load
Add Email address and testCustomerBefore load
Review and add Topic PagesCustomerBefore load
Review and test Message TemplatesCustomerBefore load
Provide LogoCustomerBefore load
Provide images for Banners/CarouselsCustomerBefore load
Add Shipping Credentials if applicableCustomerBefore load
Add PickUp Points if applicableCustomerBefore load
Add Payment Credentials if applicableCustomerBefore load
Phase 5 Data load Est. 1h FocusPoint
Week 7. Milestone: Data Load Complete. Encourage customer to load a small test batch first. Bad data in TEST will cause UAT failure.
TaskOwnerTimingPM notes
Customer loads productsCustomerWeek 71h FocusPoint support. Dep: SAP DTW Training
Customer loads Business Partners and ContactsCustomerWeek 7
Review DTW if neededImplementation ManagerWeek 7
Schedule follow-up calls if neededImplementation ManagerWeek 7
▶ SFTP / External Images only
Customer loads images and runs bulk image uploadCustomerWeek 7
Add images to SFTPCustomerWeek 7
Load Images TemplateCustomerWeek 7
Phase 6 Configuration Est. 6h FocusPoint
Week 4-8. General config runs from Week 4. Pricing config runs after data is loaded in Week 7.
TaskOwnerTimingPM notes
Configure TaxesImplementation ManagerWeek 4General config
Configure Pickup points and create shipping taskImplementation ManagerWeek 4
Configure Site Access and create tasks if neededImplementation ManagerWeek 4
Configure Inventory displayImplementation ManagerWeek 4
Configure Ordering/CheckoutImplementation ManagerWeek 4
Configure Grid/Portal orderingImplementation ManagerWeek 4
Configure Languages and CurrenciesImplementation ManagerWeek 4
Configure Payment MethodsImplementation ManagerWeek 4
Configure Shipping MethodsImplementation ManagerWeek 4
Create tasks for any complex configurationsImplementation ManagerWeek 4
Go over pricing in trainingImplementation ManagerWeek 7Pricing config. After data loaded.
Verify pricing after data loadSAP DeveloperWeek 7
Go over period/volume discounts, special and tier pricingImplementation ManagerWeek 7
Provide Credentials for Payment/ShippingSAP DeveloperWeek 7If applicable
Internal session to review Blueprint post-configSAP DeveloperWeek 7
Phase 7 Site design Est. 1h FocusPoint
Week 8-10. Mostly customer-owned. PM confirms completion before UAT.
TaskOwnerTimingPM notes
Add Topic PagesCustomerWeek 8-10
Add BannersCustomerWeek 8-10
Complete message template reviewCustomerWeek 8-10
Add Favicon to siteCustomerWeek 8-10
Provide LogoCustomerWeek 8-10
Provide images for Banners/CarouselsCustomerWeek 8-10
Remove FocusPoint from Browser TabImplementation ManagerWeek 8-10Easy to forget. Add to Go Live checklist.
Phase 8 Quality assurance and UAT Est. 3h FocusPoint
Week 9-10. Milestone: Testing Complete. FocusPoint completes internal QA first, then schedules UAT session with customer.
TaskOwnerTimingPM notes
Request access to ProdImplementation ManagerWeek 9FP internal QA
Review LinksImplementation ManagerWeek 9
Review Banners and LogosImplementation ManagerWeek 9
Review Product SearchImplementation ManagerWeek 9
Review Order processImplementation ManagerWeek 9
Review TaxesImplementation ManagerWeek 9
Review ShippingImplementation ManagerWeek 9
Review PricingImplementation ManagerWeek 9
Review any customizationsImplementation ManagerWeek 9
Review Warehouse detailsImplementation ManagerWeek 9
Review Message Templates and Topic PagesImplementation ManagerWeek 9
Test Email to ensure it worksImplementation ManagerWeek 9
Review Sales Rep Set UpImplementation ManagerWeek 9If applicable
Review Manager ApprovalsImplementation ManagerWeek 9If applicable
Schedule session to explain UAT to customerImplementation ManagerWeek 104h. Dep: Customer data loaded
Session to cover UAT with customerImplementation ManagerWeek 10
Customer completes UATCustomerWeek 10Product Search, Pricing, Display, Images, Orders, Taxes, Shipping, Message Templates, Order Portal, My Orders, additional Workflows
Phase 9 Production and Go Live Est. 10.5h FocusPoint
Week 11-12. Milestone: Go Live. Production SAP access must be confirmed at least 1 week before Go Live. Notify customer to contact domain provider in advance.
TaskOwnerTimingPM notes
Verify access to Prod with full permissionsImplementation ManagerWeek 112h. Dep: UAT complete
Schedule Go Live Checklist Session and send to clientImplementation ManagerWeek 11
Go Live Checklist Session with customerImplementation ManagerWeek 11Joint session
Final design items (favicon, etc.)DesignWeek 11
Install scripts in production (still connected to Test)SAP DeveloperWeek 113h. Dep: Go Live approval
Remove test data from production siteCloud ArchitectWeek 11
Remove BPs/Customers from SiteCloud ArchitectWeek 11
Clear out Message QueueCloud ArchitectWeek 11
Load DTW to production (still connected to Test)CustomerWeek 11
Repoint site to ProductionSAP DeveloperWeek 111h. Dep: Production ready
Full Item/BP/Inventory/Price syncSAP DeveloperWeek 11
Customer reviews site in ProductionCustomerWeek 11
Domain Name setupCustomerWeek 123h. Dep: Production approved
Recaptcha setupCloud ArchitectWeek 12
Add www to bindingsCloud ArchitectWeek 12
Go Live Switch DomainCloud ArchitectWeek 12
Install SSL CertificateCloud ArchitectWeek 12
License of Plugins (domain locked)Cloud ArchitectWeek 12
Final Site ValidationCloud ArchitectWeek 12
Change Store InformationImplementation ManagerWeek 12
Enable Email job schedulerCloud ArchitectWeek 12Easy to miss. Add to Go Live day checklist.
SEO tab updateCloud ArchitectWeek 12
Remove Character from EmailImplementation ManagerWeek 12
Verify URLs in Message TemplatesImplementation ManagerWeek 12
Customer provides new URL for domain bindingCustomerWeek 12
Customer changes Domain with providerCustomerWeek 12Notify FocusPoint before and after
Customer sends Bulk Welcome MessageCustomerWeek 12
Phase 10 Post-production Est. 30min
TaskOwnerTimingPM notes
1 week post-production check-in with customerImplementation ManagerWeek 12+30min
Give help desk information to customerImplementation ManagerWeek 12Hand off to support team
Additional features and hour estimates
Scoped and priced separately. Use these when planning capacity for customers with add-ons.
Add-on / Additional FeatureEst. Hours
Rep Carts8h
Multiple Currencies2h
Multiple Languages2h
3rd Party Market Resellers Product Feed/Order Sync8h
CRM Integrations8h
Social Media2h
Tax - 3rd Party2h
Payment Processor 3rd Party2h
Shipping 3rd Party2h
Customer Presentation Layer Access10h
Enhanced Order Rules4h
Product Customizer - Deployment Only10h
3PL4h
Service Portal4h
Preventive Maintenance4h
Customer Branded Mobile App4h
FocusPoint Mobile App10h
Solo-Deployment6h
Environment Upgrade prior to or during Implementation15h
Environment Upgrade Synced with Go Live20h
V33 as Partner3h
IT company doing Integration4h

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article